Julius Nyerere Hydropower Station: key facts

The core specifications of Tanzania’s largest power station, in one place. Where sources differ slightly on a figure, we use the most widely reported value and round it.

Installed capacity

2,115 MW

Generating units

9 vertical Francis turbines, 235 MW each

Expected annual output

About 5,920 GWh

River

Rufiji River, at Stiegler's Gorge

Regions

Pwani (Coast) and Morogoro

Main dam

Roller-compacted concrete gravity dam, about 131 m high and just over 1 km long at the crest

Reservoir

About 34 billion m³

Spillway

Central spillway with 7 radial gates

Saddle dams

4

Grid connection

400 kV substation and transmission lines

Owner and operator

TANESCO (Tanzania Electric Supply Company)

Contractor

Arab Contractors and Elsewedy Electric (Egyptian joint venture)

EPC contract

About US\$2.9 billion, awarded December 2018

Total reported cost

TZS 7.45 trillion, financed by the Government of Tanzania

Construction began

2019

First power to grid

February 2024

Official inauguration

22 August 2026